Real Project Management 101: Is the Gantt Chart Still Necessary?

10/29/2020

0 Comments

 
Picture
Ah the Gantt chart. Twenty years ago that was project management. I worked on a large government project - more like a program, actually - where the only thing I was really using the project management tool for was to manage the project schedule comprised of more than 7600 tasks and show my government project customer visually that we were on time for deliverables and milestones. It did the job well and I could create custom reports and pull task list sections out for functional department managers to track down and report status on every week during our internal project review meetings that I led. But the heart of the project management and tracking effort centered around that visual depiction of the overall project status.


Fast forward twenty years and where are we now? What's important now? What does management want to see? What does the client want to see... need to see? What about the team? What's still relevant and what's important today? Let's consider...


The status report. The status report is necessary. It will always be a critical, driving force of project status and likely the main communication tool for any weekly project customer meeting and weekly or daily project team meetings. Prepare it in advance, use it to drive the meetings, and come up with one good version that satisfies all stakeholders needs as well as possible. C-levels like quick view dashboards so start off with that – preferably coming up with a green-yellow-red health status view of task progress, resource usage and forecasting, and financial analysis and forecasting. Include change orders and issues lists on the report and you should be able to make everyone happy. Having a great project management tool that can do much of this for you is a good idea as you – as the project manager – likely already have enough on your plate. But the status report – and a very good one – is critical.


The team meetings. Team meetings – the internal team is what I'm talking about – are critical. This is where you discuss strategy and get all of the latest updates from your team that drive the status report info and the revisions to the project schedule. I like to schedule this the day before the weekly customer status meeting so that I'm always giving the project customer the latest greatest information about the health and progress of the project.


The customer status meeting. The weekly project status meeting that includes the customer is where you lay out all the information. The status report, the change order statuses, the issues, the risks, the resource forecast, the financial health if that is relevant to the customer... everything. But the project status report usually drives this meeting. And yes, one other thing often still drives it and I will get to that shortly.


Project communications. Project communications are Job One for the project manager. This includes the status report, emails, conference calls, the weekly customer status meeting and review and any deliverable and milestone reviews you may need to schedule. All materials build into the project communications – making the project status report and other items that are involved with detailing project status critical pieces of the overall project communications.


The Gantt Chart. And now we are to the Gantt Chart. Is it still relevant? Yes, it most definitely is. Whether the customer wants to see it or needs to see it may be up to them. But what it depicts and what it tracks is absolutely necessary. From task dependencies, to levels of effort, tracking holidays and progress complete percentages... the good old standards from project management days gone by are still very relevant today. Can you do with out it? Not likely. Should your project management tool be able to produce a good, usable project Gantt Chart that is visually meaningful? Yes, most definitely.


Summary / call for input


So my conclusion is this... the Gantt Chart is still necessary. What is your take? Do you need a Gantt Chart or use a Gantt Chart every week on your project? If not, what do you do? If so, tell us about your favorite tricks and even about your favorite PM tool that creates the Gantt Chart for you.

0 Comments

Your comment will be posted after it is approved.


Leave a Reply.

    Author:

    Picture

    Brad Egeland


    Named the "#1 Provider of Project Management Content in the World," Brad Egeland has over 25 years of professional IT experience as a developer, manager, project manager, cybersecurity enthusiast, consultant and author.  He has written more than 8,000 expert online articles, eBooks, white papers and video articles for clients worldwide.  If you want Brad to write for your site, contact him. Want your content on this blog and promoted? Contact him. Looking for advice/menoring? Contact him.

    Picture
    Picture
    Picture
    Picture
    Picture
    Picture

    RSS Feed

    Archives

    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    March 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    June 2010
    May 2010
    April 2010
    March 2010
    November 2009

    RSS Feed

Powered by Create your own unique website with customizable templates.