Transferring Lessons Learned to Others

9/20/2010

2 Comments

 
Back in February 2009 I wrote an article entitled “Lessons Learned” which discussed how and when to conduct Lessons Learned sessions, how to document them and what benefit they can be to others.

Since I believe that the process of review and documenting Lessons Learned is critical to every project manager in making them better PMs in the future as well as critical to the organization’s future success, I’m always looking for more information on the subject. I found it in Gary Heerkens’ book “Project Management” and I’ve included his information on the Lessons Learned process below.

How to Transfer What You’ve Learned to OthersOne of the ways you can support the ongoing improvement of your organization’s project execution methods comes in the form of lessons learned studies. The purpose of a lessons learned study is to obtain information through the systematic review of project experiences. Understanding the nature of positive and negative experiences allows future projects to avoid unfavorable influences (problems), and exploit favorable opportunities.

You should include input from all key stakeholders in your study, with you and the project team typically taking a leading role in organizing and carrying out the study. The format and structure of your lessons learned sessions (i.e., the logistics) can vary, but it is often done in a team meeting context, using an approach similar to brainstorming.

The Lessons Learned Process

You will probably find the lessons learned process to be most productive when it is oriented toward identifying problems you and your team encountered, and suggesting ways to avoid similar problems in the future. You can accomplish this by asking the following questions for each identified problem:

What was the problem and its impact? Get a description of the perceived problem and its specific effect(s) on the project. In other words, find out what happened to the project as a result of the problem.

What caused this problem to occur? Find out the known or perceived root cause of the problem. If unknown, the cost of securing this knowledge needs to be weighed against its potential benefit.

Why was the problem undetected? This involves a search for possible flaws in monitoring, control, or reporting methods. Caution: This question can also be sensitive, as it may involve individual performance problems.

Can this problem be eliminated in the future? Here you’re asking for suggestions on specific steps aimed at precluding a future occurrence. Total elimination is not always possible; however you can come up with strategies for reducing the probability of it happening again.

If it cannot be eliminated, are there ways it could be detected? Here you’re looking for suggestions on how the team can alter monitoring, control, or reporting methods in ways that allow for earlier or more reliable detection of the problem.

Tips on Conducting Effective Lessons Learned Studies

In addition to following the process steps outlined above, consider these tips for ensuring a relatively painless and effective experience for everyone involved:

Don’t wait until the end of the project to solicit input. Waiting until the last minute to conduct lessons learned studies can be problematic. Your team may have partially dissolved, making it difficult to get everyone together. Even if you do get them together, the enthusiasm level may not be what you’d like. Finally, it can be taxing on the memories of those involved, and you may get input that’s been altered by the passage of time. Conduct sessions periodically—either at the end of a logical phase of the project, or at some regular interval of team meetings.

Allow the opportunity for submitting input anonymously. As mentioned above, this may allow information and ideas to reach you that are unlikely to surface in group sessions, or would not be appropriate.

Maintain up-to-date and accurate records. This reduces the reliance on people’s memories. It will also facilitate the process of determining root causes, verifying the extent of problems, correlating possible causes and effects, etc.

Be sure to examine successes as well as problems. Reviewing positive effects can reinforce the value of certain methods, particularly the ones that people tend to avoid or undervalue.

Tips on Getting Others to Implement Your Lessons

It’s one thing to alert others to the problems you faced and to provide information about what you and your team have encountered. However, if you do not structure your information so that others can actually apply the lessons you’ve learned, your organization hasn’t really benefited. Below are some suggestions on ensuring that your wisdom is acted on:

Don’t relate lessons learned only to the specific context of your project. Make sure you express lessons learned in general terms in order to benefit the organization at large. Generalize the conclusions from your project’s lessons learned in a way that’s meaningful to the widest possible audience.

Don’t just communicate “what went well” and “what didn’t.” Unfortunately, some lessons learned studies are little more than a brain dump of what went well and what didn’t go well. A lack of analysis—or synthesis—fails to provide others in the organization with any real “lesson.” For others to benefit, they need to know how to avoid the problems or to reduce the impact if the problem occurs.

Include lessons learned reviews as a front-end activity in the project life cycle. Lessons learned studies are traditionally thought of as concluding activities only. This one-dimensional view fails to ensure their application by future project teams. Some organizations have addressed this problem by including a step near the beginning of their project process that obligates project teams to review lessons learned files as part of their up-front planning. This strategy “closes the loop” on the learning cycle and helps to ensure that the team actually applies these lessons.

I originally authored this article for the PM Tips website - the original post appears here.
2 Comments
Air Jordan link
2/16/2011 11:21:53 am

Expect people to be better than they are; it helps them to become better. But don't be disappointed when they are not; it helps them to keep trying. Do you think so?

Reply
Pastillas dieta link
3/16/2011 01:29:16 pm

It's nice to share lessons and knowledge to others.Ahm,it is one of God's message to us to share our blessings to others.

Reply



Leave a Reply.

    Author:

    Picture

    Brad Egeland


    Named the "#1 Provider of Project Management Content in the World," Brad Egeland has over 25 years of professional IT experience as a developer, manager, project manager, consultant and author.  He has written more than 7,000 expert online articles, eBooks, white papers and video articles for clients worldwide.  If you want Brad to write for your site, contact him. Want your content on this blog and promoted? Contact him. Looking for advice/menoring? Contact him.

    RSS Feed

    Picture
    Picture
    Picture
    Picture

    Archives

    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    March 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    June 2010
    May 2010
    April 2010
    March 2010
    November 2009

    RSS Feed

Powered by Create your own unique website with customizable templates.