When You Must Adjust the Project Schedule

7/23/2020

0 Comments

 
Picture
Picture
Sometimes you run into an impossible situation with the project schedule and it must be adjusted. It can be for a number of reasons, but the two main reasons usually come down to these: resource usage or conflicts and the need to meet a forced deadline.


Adjusting the schedule for resource needs or loading


If you find yourself stuck resource-wise and you must make schedule adjustments as a result, there are few options you have and a few things to take into consideration.


  • Change the scope of the project or add resources. You can possibly change the size of the project (up or down) and/or add project resources – but keep in mind that more resources always mean more cost. Approval from above will be required.
 
  • Add time to a task. Give a task more time or spilt it in two, modifying resource utilization to make the process work. You can also adjust the basic finish-to-start precedence relationships (if appropriate) by adding lead or lag time to tasks that enable some of the work to occur in parallel.
 
  • Move tasks around to when resources are available. Move a task to a time when more resources are free. This will mean calculating the entire schedule again to make sure the moved task doesn’t impact the critical path of the project.
 
  • Outsource the work. Remember that outsourcing work, while reducing work done by the implementation team, also adds new tasks for vendor management and it can also increase the cost of the task and therefore negatively impact the project budget.
 
  • Negotiate additional time. Negotiate additional time in the schedule with a later completion date and a budget increase. Stakeholder agreement will be needed in order for this to happen and avoid negotiation the time required to complete the tasks because these should be good estimates at this point in the project.
 
  • Reprioritize the goals and scope of the project. Possibly reduce the number of project deliverables and goals for the project as a whole. This is a long shot and will require review and approval of the key project stakeholders.
 
  • Use a phased approach. This is my go to solution for key scheduling issues. Work with the project customer to negotiate delivering components of the project in a phased approach, thereby extending the total project schedule but still giving the customer acceptable products or services.
 
  • Find resources that may be a better fit. This one will be difficult as we usually can’t get resources switched out on our projects – at least not without a lot of give and take. Plus, this option may increase the budget, so be careful even if it is something you can pursue.


Adjusting the schedule to meet a deadline


Many projects have a forced or dictated deadline. A customer may need a project completed by a specific date, someone in your organization may have published a date in a trade journal when an output of the project will be ready (this one happened to me), or it may be a government project and the end delivery date just isn’t negotiable – at least not without considerable liquidated damages or fines as a result…which is usually not something your senior management will be ok with.


Such a project should start as early as possible in case unforeseen delays slow completion. If your careful scheduling shows that a project due date is impossible, you have three alternatives:


Reduce the scope of the project. Good luck – but you may be able to negotiate this if you can truly show that it’s never going to work but the key functionality can be delivered on time if you the scope is reduced.


Add additional resources. This is always a costly option, but it may be the only option if it absolutely must be done by ‘x’.


Work out a due date extension. Work out some way to extend the completion date (not always possible). I realize we said this isn’t an option, but never say never. You can always try.


If it isn’t possible to make adjustments to realign the tasks to the schedule, you’ll need to renegotiate the cost-schedule-results equilibrium with the key stakeholders. This is not the fun part of project management, but is the necessary next step for the project manager.
0 Comments

Your comment will be posted after it is approved.


Leave a Reply.

    Author:

    Picture

    Brad Egeland


    Named the "#1 Provider of Project Management Content in the World," Brad Egeland has over 25 years of professional IT experience as a developer, manager, project manager, cybersecurity enthusiast, consultant and author.  He has written more than 8,000 expert online articles, eBooks, white papers and video articles for clients worldwide.  If you want Brad to write for your site, contact him. Want your content on this blog and promoted? Contact him. Looking for advice/menoring? Contact him.

    Picture
    Picture
    Picture
    Picture
    Picture
    Picture

    RSS Feed

    Archives

    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    March 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    June 2010
    May 2010
    April 2010
    March 2010
    November 2009

    RSS Feed

Powered by Create your own unique website with customizable templates.